Execution method

Thirteen roof steps and eight wet-area steps, in the exact site sequence, with the waiting times and hold points that may not be skipped.

13 STEPS

Part 1: Roofs

01
STEP 01 — SURVEY AND DECK ACCEPTANCE

Survey and deck acceptance

Our engineers inspect the roof and set the client’s requirements before Combo works proceed. The following must be in place:

  • Locate electrical, water, cooling, data and lightning-protection services
  • Rainwater outlets at 3 cm above deck, projecting 20–25 cm, correctly falling and fixed
  • Loads over 1 t/m² need concrete plinths or a steel frame before the system starts
  • Upstands at door and light-well openings, height set by distance to the drains
  • Brick construction: internal wall and parapet must be plastered first
  • Any drain filters must be fixed before works begin
  • Deck cleared of debris and plaster residue; all conflicting works completed
Note: these items are the client’s responsibility; we can carry out some of them by agreement.
02
STEP 02

Deck cleaning and wall masking

Compressed-air cleaning; upstands and fixtures masked to 50 cm against overspray.

03
STEP 03

Spraying the PU foam

Spray-applied PU foam, 3–4 cm or more, density not less than 40–45 kg/m³: high thermal insulation, plus water and sound.

04
STEP 04

Rubberised waterproof coat

Rubberised liquid waterproof coat over the foam — the first line of defence.

05
STEP 05

First flood test (24 h)

Hold point

After 24 h the roof is flooded for 24 h; a pass is recorded in a signed report, then drained.

06
STEP 06

Geotextile protection layer

120 g/m² geotextile to protect and separate the coatings from the screed.

07
STEP 07

Fibre-board expansion joints

Bitumen-impregnated fibre boards set in mortar to the agreed falls.

08
STEP 08

Screed and power-float

Unreinforced screed, power-floated to guarantee run-off.

09
STEP 09

Cutting joints after 7 days

Hold point

Seven days after pouring the joints are cut straight and the fibre board removed.

10
STEP 10

Filling the movement joints

Backer rod plus polyurethane mastic to absorb movement.

11
STEP 11

Perimeter fillets

45° sand-cement fillets with fabric or plastic mesh tape.

12
STEP 12

Primer coat

Exterior primer, UV and weather resistant.

13
STEP 13

Final top coat

Reflective epoxy/PU top coat closes the system.

WET AREAS — 8 STEPS

Part 2: Bathrooms and balconies

Bathrooms and balconies get their own system, separate from the roof: a flexible cementitious membrane in two crossed coats, preceded by careful treatment of pipe penetrations and floor-to-wall junctions, the two places wet-area leaks most often start.

Balcony after both flexible cementitious coats
01

Removing plaster residue

Hammer-drill removal of plaster residue.

02

Grinding the substrate

Grinding to an even substrate.

03

Compressed-air cleaning

Blowing the surface clean of dust.

04

Sealing pipe penetrations

Core holes sealed with 8 mm backer rod and grout around pipes.

05

45° fillet

45° fillet, at least 5 cm high, with door openings dammed.

06

Mesh tape at corners

Mesh tape bedded over all fillets for a continuous membrane.

07

Flexible cementitious membrane

First coat lengthways; second coat crossways after 24 h.

08

Flood test and handover

24-hour flood test before handover.