Survey and deck acceptance
Our engineers inspect the roof and set the client’s requirements before Combo works proceed. The following must be in place:
- Locate electrical, water, cooling, data and lightning-protection services
- Rainwater outlets at 3 cm above deck, projecting 20–25 cm, correctly falling and fixed
- Loads over 1 t/m² need concrete plinths or a steel frame before the system starts
- Upstands at door and light-well openings, height set by distance to the drains
- Brick construction: internal wall and parapet must be plastered first
- Any drain filters must be fixed before works begin
- Deck cleared of debris and plaster residue; all conflicting works completed